InterContinental Suites Hotel
★ CLEVELAND, OHIO — CLEVELAND CLINIC CAMPUS
A Complete Floor-by-Floor Renovation Turnover — One of the Largest Single Engagements in Company History
In 2011, North Coast Hotel Liquidators managed the complete guestroom liquidation and FF&E turnover for the InterContinental Suites Hotel on the Cleveland Clinic campus — stripping the property floor by floor while simultaneously receiving, warehousing, and placing all-new furnishings arriving by overseas container. It remains one of the most significant projects in company history.
.jpeg)
THE CHALLENGE
• Fully liquidate hundreds of existing guestrooms floor by floor without disrupting an active renovation schedule
• Simultaneously receive, inventory, and stage new FF&E arriving by overseas ocean container
• Coordinate hand-in-hand with the general contractor on install, unwrapping, and placement
• Secure and manage an off-site warehouse near the property, funded by Cleveland Clinic
•Responsibly dispose of all packaging and shipping materials from the new inventory
OUR SOLUTION
• NCHL cleared existing guestroom FF&E on a rolling, floor-by-floor basis, timed precisely against the renovation schedule so the contractor always had cleared floors ready to work.
• In parallel, all-new FF&E arriving from overseas by ocean container was received, inventoried, and unloaded at a dedicated off-site warehouse close to the hotel — secured and paid for by Cleveland Clinic to support the project.
• NCHL worked hand-in-hand with the general contractor as new inventory was placed — staging, unwrapping, and responsibly disposing of all packaging, while the contractor handled fixed mounting and installation.
• The scale and complexity of running full liquidation and new FF&E placement side by side made this one of the most demanding — and most successful — engagements NCHL has completed.
RESULTS
• One of the largest single engagements in NCHL company history
• Full guestroom liquidation completed floor by floor with zero disruption to the renovation schedule
• Successfully managed simultaneous outbound liquidation and inbound overseas container receiving
• Secured and operated an off-site warehouse in close coordination with Cleveland Clinic
• Built a close, trusted working relationship with the general contractor that carried into future phases
• Became the most profitable project NCHL had completed to that point